<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article
PUBLIC "-//NLM//DTD JATS (Z39.96) Journal Publishing DTD v1.4 20190208//EN"
       "JATS-journalpublishing1.dtd">
<article xmlns:mml="http://www.w3.org/1998/Math/MathML" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" article-type="research-article" dtd-version="1.4" xml:lang="en">
 <front>
  <journal-meta>
   <journal-id journal-id-type="publisher-id">Construction and Architecture</journal-id>
   <journal-title-group>
    <journal-title xml:lang="en">Construction and Architecture</journal-title>
    <trans-title-group xml:lang="ru">
     <trans-title>Строительство и архитектура</trans-title>
    </trans-title-group>
   </journal-title-group>
   <issn publication-format="print">2308-0191</issn>
   <issn publication-format="online">2500-1477</issn>
  </journal-meta>
  <article-meta>
   <article-id pub-id-type="publisher-id">6a84bc8294fbba14f786a112</article-id>
   <article-id pub-id-type="doi">10.29039/2308-0191-2024-12-2-3-3</article-id>
   <article-id pub-id-type="edn">mhatep</article-id>
   <article-categories>
    <subj-group subj-group-type="toc-heading" xml:lang="ru">
     <subject>2.1.7. ТЕХНОЛОГИЯ И ОРГАНИЗАЦИЯ СТРОИТЕЛЬСТВА (ТЕХНИЧЕСКИЕ НАУКИ)</subject>
    </subj-group>
    <subj-group subj-group-type="toc-heading" xml:lang="en">
     <subject>2.1.7. TECHNOLOGY AND ORGANIZATION OF CONSTRUCTION (TECHNICAL SCIENCES)</subject>
    </subj-group>
    <subj-group>
     <subject>2.1.7. ТЕХНОЛОГИЯ И ОРГАНИЗАЦИЯ СТРОИТЕЛЬСТВА (ТЕХНИЧЕСКИЕ НАУКИ)</subject>
    </subj-group>
   </article-categories>
   <title-group>
    <article-title xml:lang="en">Time reservation during construction of large-scale projects</article-title>
    <trans-title-group xml:lang="ru">
     <trans-title>Резервирование времени при строительстве крупных объектов</trans-title>
    </trans-title-group>
   </title-group>
   <contrib-group content-type="authors">
    <contrib contrib-type="author">
     <name-alternatives>
      <name xml:lang="ru">
       <surname>Павлов</surname>
       <given-names>Александр Сергеевич</given-names>
      </name>
      <name xml:lang="en">
       <surname>Pavlov</surname>
       <given-names>Aleksandr Sergeevich</given-names>
      </name>
     </name-alternatives>
     <email>building2020@inbox.ru</email>
     <bio xml:lang="ru">
      <p>доктор технических наук;</p>
     </bio>
     <bio xml:lang="en">
      <p>doctor of technical sciences;</p>
     </bio>
     <xref ref-type="aff" rid="aff-1"/>
    </contrib>
    <contrib contrib-type="author">
     <name-alternatives>
      <name xml:lang="ru">
       <surname>Островский</surname>
       <given-names>Роман Вадимович</given-names>
      </name>
      <name xml:lang="en">
       <surname>Ostrovskiy</surname>
       <given-names>Roman Vadimovich</given-names>
      </name>
     </name-alternatives>
     <email>rchkp@rambler.ru</email>
     <bio xml:lang="ru">
      <p>аспирант технических наук;</p>
     </bio>
     <bio xml:lang="en">
      <p>graduate student of technical sciences;</p>
     </bio>
     <xref ref-type="aff" rid="aff-1"/>
     <xref ref-type="aff" rid="aff-2"/>
    </contrib>
   </contrib-group>
   <aff-alternatives id="aff-1">
    <aff>
     <institution xml:lang="ru">Московский государственный строительный университет</institution>
    </aff>
    <aff>
     <institution xml:lang="en">Moscow State University of Civil Engineering </institution>
    </aff>
   </aff-alternatives>
   <aff-alternatives id="aff-2">
    <aff>
     <institution xml:lang="ru">АО «Атомстройэкспорт»</institution>
     <city>Москва</city>
     <country>Россия</country>
    </aff>
    <aff>
     <institution xml:lang="en">JSC Atomstroyexport</institution>
     <city>Moscow</city>
     <country>Russian Federation</country>
    </aff>
   </aff-alternatives>
   <pub-date publication-format="print" date-type="pub" iso-8601-date="2024-06-20T14:24:01+03:00">
    <day>20</day>
    <month>06</month>
    <year>2024</year>
   </pub-date>
   <pub-date publication-format="electronic" date-type="pub" iso-8601-date="2024-06-20T14:24:01+03:00">
    <day>20</day>
    <month>06</month>
    <year>2024</year>
   </pub-date>
   <fpage>3</fpage>
   <lpage>3</lpage>
   <history>
    <date date-type="received" iso-8601-date="2024-04-26T00:00:00+03:00">
     <day>26</day>
     <month>04</month>
     <year>2024</year>
    </date>
    <date date-type="accepted" iso-8601-date="2024-05-05T00:00:00+03:00">
     <day>05</day>
     <month>05</month>
     <year>2024</year>
    </date>
   </history>
   <permissions>
    <copyright-statement xml:lang="ru">© 2024 Павлов А.С., Островский Р.В.</copyright-statement>
    <copyright-statement xml:lang="en">© 2024 Pavlov A.S., Ostrovskiy R.V.</copyright-statement>
    <copyright-year>2024</copyright-year>
    <copyright-holder xml:lang="ru">Павлов Александр Сергеевич, Островский Роман Вадимович</copyright-holder>
    <copyright-holder xml:lang="en">Pavlov Aleksandr Sergeevich, Ostrovskiy Roman Vadimovich</copyright-holder>
   </permissions>
   <self-uri xlink:href="https://build-pro.editorum.ru/en/nauka/publications/6a84bc8294fbba14f786a112/view">https://build-pro.editorum.ru/en/nauka/publications/6a84bc8294fbba14f786a112/view</self-uri>
   <abstract xml:lang="ru">
    <p>В статье рассматривается область управления сроками жизненного цикла сооружения крупномасштабных и технически сложных уникальных объектов. В частности, авторами исследования поднимается вопрос резервирования времени для компенсации рисков несвоевременного выполнения подрядных работ и срыва сроков ввода в строй объектов строительства. Проведен обзор нормативной, законодательной и научной базы по тематике исследования.&#13;
Приводится методика распределения резерва времени между участниками проекта по восходящей или нисходящей схеме в зависимости от исходных условий. При этом подчеркивается важность включения в календарный план строительства результатов расчета распределения резерва времени.&#13;
Представлена формула расчета затрат, зависящих от величины определенного резерва. Ее можно представить в виде суммы вероятного значения неустоек, оплачиваемых при отставании порученных подрядчику работ, и дополнительных затрат, возникающих при создании увеличенной мощности строительно-монтажной организации.</p>
   </abstract>
   <trans-abstract xml:lang="en">
    <p>The article considers the area of life cycle time management of construction of large-scale and technically complex unique objects. In particular, the authors of the study raise the issue of time reservation to compensate for the risks of untimely fulfillment of contractual works and failure of commissioning of construction projects. The review of normative, legislative and scientific base on the subject of the research is carried out.&#13;
The methodology of time reserve distribution between the project participants according to the ascending or descending scheme depending on the initial conditions is given. It is emphasized the importance of including the results of the calculation of time reserve allocation in the construction schedule.&#13;
The formula for calculating the costs that depend on the value of a certain reserve is presented. It can be represented as the sum of the probable value of penalties payable in case of delay in the works assigned to the contractor, and additional costs arising from the creation of increased capacity of the construction and assembly organization.</p>
   </trans-abstract>
   <kwd-group xml:lang="ru">
    <kwd>строительство крупных объектов</kwd>
    <kwd>резервирование времени</kwd>
    <kwd>сроки строительства</kwd>
    <kwd>календарно-сетевое планирование</kwd>
    <kwd>управление рисками строительства</kwd>
    <kwd>проект организации строительства</kwd>
    <kwd>критический путь</kwd>
   </kwd-group>
   <kwd-group xml:lang="en">
    <kwd>construction of large-scale projects</kwd>
    <kwd>time reservation</kwd>
    <kwd>construction timing</kwd>
    <kwd>schedule and network planning</kwd>
    <kwd>construction risk management</kwd>
    <kwd>construction organization project</kwd>
    <kwd>critical path</kwd>
   </kwd-group>
  </article-meta>
 </front>
 <body>
  <p></p>
 </body>
 <back>
  <ref-list>
   <ref id="B1">
    <label>1.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Никитенко, А. В. Развитие теории и методологии управления рисками инвестиционных проектов / А. В. Никитенко // Экономика и социум: современные модели развития. – 2017. – № 16. – С. 75-88. – EDN ZSWOPP.</mixed-citation>
     <mixed-citation xml:lang="en">Nikitenko, A. V. Development of the theory and methodology of investment projects risk management / A. V. Nikitenko // Economy and society: modern models of development. – 2017. – № 16. – S. 75-88. – EDN ZSWOPP.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B2">
    <label>2.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Фетисов, А. Ю. Приемы и методы управления налоговыми рисками на предприятии сферы жилищного строительства / А. Ю. Фетисов, Т. Ю. Серебрякова // Вестник Российского университета кооперации. – 2018. – № 1(31). – С. 80-83. – EDN YVAUIR.</mixed-citation>
     <mixed-citation xml:lang="en">Fetisov, A. Yu. Methods and techniques of tax risk management at the enterprise of housing construction / A. Yu. Fetisov, T. Yu. Serebryakova // Bulletin of the Russian University of Cooperation. – 2018. – № 1(31). – S. 80-83. – EDN YVAUIR.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B3">
    <label>3.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Чиненова, Д. А. Риски и методы управлениями ими при строительстве нефтегазопроводов / Д. А. Чиненова // E-Scio. – 2023. – № 4(79). – С. 452-459. – EDN NZDPNC.</mixed-citation>
     <mixed-citation xml:lang="en">Chinenova, D. A. Risks and methods of risk management in oil and gas pipeline construction / D. A. Chinenova // E-Scio. – 2023. – № 4(79). – S. 452-459. – EDN NZDPNC.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B4">
    <label>4.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Павлов, А. С. Государственные закупки в строительстве - предложения по совершенствованию / А. С. Павлов, Р. В. Островский // Вестник МГСУ. – 2022. – Т. 17, № 4. – С. 501-515. – DOI 10.22227/1997-0935.2022.4.501-515. – EDN WZAVQH.</mixed-citation>
     <mixed-citation xml:lang="en">Pavlov, A. S. Public procurement in construction - suggestions for improvement / A. S. Pavlov, R. V. Ostrovsky // Vestnik MGSU. – 2022. – T. 17, № 4. – S. 501-515. – DOI 10.22227/1997-0935.2022.4.501-515. – EDN WZAVQH.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B5">
    <label>5.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Клыков, М. С. Оптимизация временного резервирования потребности в складируемых ресурсах с учетом надежности мостостроительного расписания / М. С. Клыков, А. В. Земсков // Дальний Восток: проблемы развития архитектурно-строительного комплекса. – 2014. – № 1. – С. 249-253. – EDN TBREMB.</mixed-citation>
     <mixed-citation xml:lang="en">Klykov, M. S. Optimization of temporary reservation of the need in stored resources taking into account the reliability of the bridge construction schedule / M. S. Klykov, A. V. Zemskov // Far East: problems of development of the architectural and construction complex. – 2014. – № 1. – S. 249-253. – EDN TBREMB.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B6">
    <label>6.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Никоноров, С. В. Повышение организационно-технологической надежности строительства в современных условиях / С. В. Никоноров, А. А. Мельник // Вестник Южно-Уральского государственного университета. Серия: Строительство и архитектура. – 2019. – Т. 19, № 3. – С. 19-23. – DOI 10.14529/build190303. – EDN JQRUNE.</mixed-citation>
     <mixed-citation xml:lang="en">Nikonorov, S. V. Increase of organizational and technological reliability of construction in modern conditions / S. V. Nikonorov, A. A. Melnik // Bulletin of South Ural State University. Series: Construction and Architecture. – 2019. – T. 19, № 3. – S. 19-23. – DOI 10.14529/build190303. – EDN JQRUNE.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B7">
    <label>7.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Бондаренко, Ю. В. Математические методы поддержки сетевого анализа проекта и оценки риска планирования при нечеткой информации о продолжительностях работ / Ю. В. Бондаренко, Е. В. Васильчикова // Вестник Воронежского государственного университета. Серия: Системный анализ и информационные технологии. – 2023. – № 2. – С. 100-111. – DOI 10.17308/sait/1995-5499/2023/2/100-111. – EDN ULOXXK.</mixed-citation>
     <mixed-citation xml:lang="en">Bondarenko, Yu. V. Mathematical methods to support project network analysis and planning risk assessment under fuzzy information about work durations / Yu. V. Bondarenko, E. V. Vasilchikova // Vestnik of Voronezh State University. Series: System Analysis and Information Technologies. – 2023. – № 2. – S. 100-111. – DOI 10.17308/sait/1995-5499/2023/2/100-111. – EDN ULOXXK.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B8">
    <label>8.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Kalugin, Yu. B. Universal method for calculation of reliable completion times / Yu. B. Kalugin // Magazine of Civil Engineering. – 2016. – No. 7(67). – P. 70-80. – DOI 10.5862/MCE.67.7. – EDN YFWGLB.</mixed-citation>
     <mixed-citation xml:lang="en">Kalugin, Yu. B. Universal method for calculation of reliable completion times / Yu. B. Kalugin // Magazine of Civil Engineering. – 2016. – No. 7(67). – P. 70-80. – DOI 10.5862/MCE.67.7. – EDN YFWGLB.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B9">
    <label>9.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Харчук, Е. Г. Инструментарий определения последовательности работ / Е. Г. Харчук, Е. С. Иванец // Международный научный журнал Интернаука. – 2017. – Т. 2, № 15(37). – С. 59-62. – EDN ZWLLZZ.</mixed-citation>
     <mixed-citation xml:lang="en">Harchuk, E. G. Toolkit for determining the work sequence / E. G. Kharchuk, E. S. Ivanets // International Scientific Journal Internauka. – 2017. – T. 2, № 15(37). – S. 59-62. – EDN ZWLLZZ.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B10">
    <label>10.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Будникова, И. К. Моделирование управляемых процессов с применением методов сетевого планирования / И. К. Будникова, Е. В. Приймак // Вестник Технологического университета. – 2018. – Т. 21, № 1. – С. 115-118. – EDN YRHDVN.</mixed-citation>
     <mixed-citation xml:lang="en">Budnikova, I. K. Modeling of controlled processes using network planning methods / I. K. Budnikova, E. V. Priymak // Vestnik of Technological University. – 2018. – T. 21, № 1. – S. 115-118. – EDN YRHDVN.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B11">
    <label>11.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Воронков, И. Е. Оценка факторов, влияющих на изменения длительности сооружения АЭС / И. Е. Воронков, Р. В. Островский, И. Г. Агапов // Строительное производство. – 2023. – № 4. – С. 105-110. – DOI 10.54950/26585340_2023_4_105. – EDN ZDLBHO.</mixed-citation>
     <mixed-citation xml:lang="en">Voronkov, I. E. Evaluation of factors influencing changes in the duration of NPP construction / I. E. Voronkov, R. V. Ostrovskiy, I. G. Agapov // Construction Production. – 2023. – № 4. – S. 105-110. – DOI 10.54950/26585340_2023_4_105. – EDN ZDLBHO.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B12">
    <label>12.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Болотин, С. А. Энтропия актуального графика строительства / С. А. Болотин, А. Х. Дадар, Р. А. Магамадов // Вестник гражданских инженеров. – 2016. – № 3(56). – С. 123-129. – EDN WHFDZR.</mixed-citation>
     <mixed-citation xml:lang="en">Bolotin, S. A. Entropy of the actual construction schedule / S. A. Bolotin, A. H. Dadar, R. A. Magamadov // Bulletin of Civil Engineers. – 2016. – № 3(56). – S. 123-129. – EDN WHFDZR.</mixed-citation>
    </citation-alternatives>
   </ref>
   <ref id="B13">
    <label>13.</label>
    <citation-alternatives>
     <mixed-citation xml:lang="ru">Павлов, А. С. Анализ сроков выполнения работ при сооружении атомных электростанций / А. С. Павлов, Р. В. Островский // Промышленное и гражданское строительство. – 2023. – № 1. – С. 75-80. – DOI 10.33622/0869-7019.2023.01.75-80. – EDN TZYWUH.</mixed-citation>
     <mixed-citation xml:lang="en">Pavlov, A. S. Analysis of work execution time during the construction of nuclear power plants / A. S. Pavlov, R. V. Ostrovsky // Industrial and Civil Construction. – 2023. – № 1. – S. 75-80. – DOI 10.33622/0869-7019.2023.01.75-80. – EDN TZYWUH.</mixed-citation>